Arizona has switched on its first fast chargers paid for by the federal NEVI program, in Tucson, Green Valley and Wellton. If you drive an EV between Phoenix, Tucson and the California or Mexico borders, they sit right on your roads.
They are the first sites open in a plan to spend a share of roughly $76 million in federal money on stations statewide. The wait has been long. Congress created NEVI in 2021, but Arizona didn't take bids for its first round until January 2024, and the first awards came that August.
A schedule that slipped
The Arizona Department of Transportation (ADOT) first said building would take about a year after contracts were signed, with some sites open by late 2025. Construction didn't actually start until early 2026.
Washington added its own delay. Early in 2025 the Trump administration paused states' approved plans and blocked new commitments while it rewrote the rules, though payments on existing agreements kept flowing. Court records show Arizona then dropped a call for more possible locations because it lost access to tens of millions of dollars not yet tied to projects.
Arizona joined other states in suing. A judge gave preliminary relief that summer and found early this year that the money had been wrongly held back. The records don't say how much the freeze set back each of the three open sites, so the lateness can't be pinned on one cause.
One caution on all of this: the account of the pause, the lawsuit and the rulings comes from a single published report, which cites court records. We have not independently confirmed the filings or the federal rule changes, and the report doesn't say exactly how long the pause lasted.
What comes next on I-40
ADOT says most stations will offer both NACS (Tesla-style) and CCS plugs, with at least four 150-kilowatt chargers at most locations. Its announcement doesn't break that down for these three sites, so check before you count on a particular plug.
Two more stations, in Seligman and Holbrook along I-40, are expected before the end of 2026. That's a target, and earlier ones have slipped. ADOT is also seeking bids for nearly 50 more locations, with proposals due in early 2027 and construction not expected to start until 2028.
So the I-40 corridor is the next gap to watch. If you've planned an Arizona road trip around a thin charging map, do three new sites change your route?
Sources
Reported by the WattsUpNext desk from the sources linked below. Spot an error? Tell us at corrections@wattsupnext.com.